Ice arena in Kartmazovo, Moscow

Integrated engineering surveys for the design of a 61 × 90 m sports complex.

Cost of a similar project at today's rates1 180 000 ₽
Contract duration, calendar days35
Site1.3 ha
Drilling12 BHs × 15 m
Proposed building layout (from the client's baseline data)
Proposed building layout (from the client's baseline data)
Survey site location
Survey site location

Objective

Execution of a full package of engineering surveys (geotechnical, topographic, environmental and hydrometeorological) for the design of a two-storey ice palace measuring 61 × 90 m in the village of Kartmazovo (Moskovsky settlement). The documentation was prepared for state expert review and the development of design and estimate documentation.

The survey site is an overgrown meadow near new residential developments with a dense network of above-ground and underground utilities. Due to waterlogging across part of the area, the locations of several exploratory holes (boreholes) were promptly adjusted in agreement with the client.

First page of the technical brief

Scope of work and deliverables

GTGeotechnical surveys

Scope of work

  • 12 boreholes 15 m deep — 180 linear metres
  • 6 cone penetration tests (CPT)
  • 44 undisturbed soil cores and 10 sand samples for laboratory testing
  • 24 triaxial compression tests, plus shear and oedometer consolidation tests
  • chemical analysis of soil and groundwater
  • excavation permit obtained

Results

  1. Geotechnical conditions — complexity category II (medium).
  2. Five engineering geological units (EGUs) were identified down to a depth of 15 m: cover and moraine sandy clays, underlain by Cretaceous sandy clays, clays and silty sands.
  3. Groundwater was encountered in all boreholes at depths of 2.5–3.6 m. In spring, the groundwater table (GWT) may rise by up to 1 m, which has been taken into account in the design solutions.
  4. Groundwater is slightly aggressive to W4 watertightness grade concrete and moderately aggressive to metal, which was taken into account when designing corrosion protection for the structures.
  5. No karst-suffosion hazard.
Geotechnical cross-section 1–1 from the technical report
Geotechnical cross-section 1–1 from the technical report
  • EGU-2 Sandy clay, very stiff, cover deposit (pQIII)
  • EGU-3 Sandy clay, stiff, with grus and gravel, glacial till (gQIIms)
  • EGU-4 Sandy clay, stiff, Cretaceous (K1)
  • EGU-5 Firm Cretaceous clay (K1)
  • EGU-6 Silty sand, dense (K1)
  • Groundwater level
Factual material map: boreholes, sounding points, cross-section lines

Legend

  • geotechnical borehole, number and depth, m
  • cone penetration test (CPT) point, number
  • geotechnical cross-section line, number
  • footprint of the proposed structure
Geotechnical surveys — about the service →

TSTopographic surveys

Scope of work

  • 1:500 engineering topographic plan for a 1.3 ha plot, contour interval 0.5 m
  • Moscow coordinate and elevation system (MGGT)
  • survey of underground and aboveground utilities
  • registration in Moscow GISOGD

Results

  1. 1:500 engineering topographic plan covering the entire 1.3 ha site, with a 0.5 m contour interval.
  2. The site relief is predominantly flat, with surface elevations ranging from 181.6 to 182.7 m.
  3. All above-ground and underground utilities are plotted on the topographic plan, which is essential for accurate building siting and utility design.
  4. The plan is registered in the Moscow State Information System for Urban Development (GISOGD).
Engineering topographic site plan, scale 1:500
Engineering topographic site plan, scale 1:500
Protocol of TS materials registration in the Moscow GISOGD dated 16.05.2025 (excerpt)
Protocol of TS materials registration in the Moscow GISOGD dated 16.05.2025 (excerpt)
Topographic surveys — about the service →

ESEnvironmental surveys

Scope of work

  • 6 soil samples: heavy metals, petroleum hydrocarbons, benzo(a)pyrene
  • microbiological and parasitological samples
  • 1.3 ha gamma survey and 14 dose rate measurement points
  • 54 radon flux density measurement points

Results

  1. Soils and ground down to a depth of 2 m meet the 'permissible' contamination category and may be used without restriction (except at high-risk facilities).
  2. Concentrations of heavy metals and benzo(a)pyrene do not exceed maximum permissible concentrations (MPC); petroleum hydrocarbon concentration is up to 424 mg/kg against a regulatory limit of 1,000 mg/kg.
  3. Microbiological and parasitological indicators — 'clean' category.
  4. Background radiation is within normal limits, with no radiation anomalies recorded. Soils are classified as Class I based on the specific effective activity of natural radionuclides. Radon flux density complies with regulatory standards.
Schematic map of environmental conditions: soil sampling boreholes and trial plots, gamma survey points and radon flux measurements
Schematic map of environmental conditions: soil sampling boreholes and trial plots, gamma survey points and radon flux measurements
Map of zones with special conditions for use of territories (ZOUIT): plot within the Vnukovo aerodrome environs
Map of zones with special conditions for use of territories (ZOUIT): plot within the Vnukovo aerodrome environs
Environmental surveys — about the service →

HMHydrometeorological surveys

Scope of work

  • climatic parameters from VDNKh weather station
  • assessment of the impact of the Setun River (510 m from the site)
  • hazardous hydrometeorological phenomena

Results

  1. The nearest watercourse (the River Setun) flows 510 m from the site and has no impact on it; there are no hazardous hydrological processes.
  2. South-westerly and westerly winds prevail (19% and 18% annually), with a mean wind speed of 2.1 m/s.
  3. Standard frost penetration depth for loams is 0.96 m.
  4. Snow region III — 1.45 kPa; wind pressure 0.23 kPa; ice region II, ice thickness 5 mm.
NNEInSESSWWNWJanuaryNNEInSESSWWNWJulyNNEInSESSWWNWYear
Wind rose for VDNKh weather station, directional frequency, %; 5% rings
Hydrometeorological surveys — about the service →

Site photos

Site before commencement of works
Site before commencement of works
Drilling a borehole next to new residential developments
Drilling a borehole next to new residential developments
Borehole 1 core: cover and moraine sandy clays
Borehole 1 core: cover and moraine sandy clays
Borehole 1 core from depth: greenish-grey Cretaceous clays
Borehole 1 core from depth: greenish-grey Cretaceous clays
Drilling rig on site
Drilling rig on site
Borehole drilling on an overgrown plot
Borehole drilling on an overgrown plot

Result

The technical reports received approval from a non-state expert review, and the engineering topographic plan was registered in the Moscow urban development information system (GISOGD).

This is just one of our projects: every year our specialists carry out surveys on 40–50 sites in Moscow, the Moscow Region, and across Russia.